For One of our Clients we're looking for a Project Lead Rotating During the 2021 outage, a major overhaul is scheduled for both gas turbine and steam turbine at the Ineos Oxide CHP. For the coordination of this work package the role of partial pro

Vacature omschrijving


The part project lead rotating is member of the Ineos oxide CHP outage organization. Within the area of rotating equipment, two main installations are located:

Siemens TLRI steam turbine
Siemens SGT 800 gas Turbine

From these two area’s the Steam turbine scope will be the focus of the part project lead. The gas turbine outage is covered by a LTSA with Siemens and in this part, the scope is limited to a supporting and facilitating role.

Regarding Steam turbine scope.

For the steam turbine a major outage (100.000 OH) is scheduled that will include opening of the casing. This will be the first major inspection of the turbine. The part project lead is responsible for minimally the following aspects:

1. Part project management including but not limited to progress reporting, financial reporting, safety reporting et cetera as specified by Ineos.
2. Scope development for the major outage, specifically noting NTD / DT Testing protocols.
3. Scoping of strategic spare parts for procurement,
4. Developing Tendering / awarding process of technical package,
5. Develop organogram for staffing of QA /QC and maintenance team for rotating area,
6. Coordination of all works in steam turbine enclosure execution of outage

Regarding gas turbine scope

1. Part project management including but not limited to progress reporting, financial reporting, safety reporting et cetera as specified by Ineos.
2. Scope execution according to activity list.
3. Developing Tendering / awarding process of technical package,
4. Coordination of all works in gas turbine enclosure execution of outage



Additional aspects may be defined for each scope area if required by Ineos in discussion with supplier.
Scope
Steam turbine
The scope for the steam turbine encloses the following aspects:

1. Steam turbine, including control, extraction and SS valves, up to the lock out valves.
2. Bearings in the whole powertrain 5x (including generator)
3. Condenser operation both steam- and waterside. Including condenser cleaning system and booster cooling system.
4. Gland steam, Vacuum system and evacuation system
5. Oil and hydraulic system including hydraulic actuators et cetera
6. Opening of enclosure including temporary roofing and storage / work area’s
7. Condensate system
8. Coupling (generator steam turbine)
9. Special tools and crane,
10. Down day tickets from maintenance department

Not included are:

A. main cooling channels. (civil)
B. HP en LP by pass stations (Mechanical) C. DCS Control system (Project)
D. Generator scope (Electrical)

Gas turbine
The scope of the gas turbine encloses the following aspects:

1. Support Siemens on Level C outage Gas turbine power train as requested,
2. Covering all activities as stated responsibility (Purchaser) in the activity list from the LTSA.
3. Opening of enclosure including temporary roofing and storage / work area’s
4. Special tools and crane,
5. Down day tickets from maintenance department

Not included are:

A. DCS Control system (Project) B. Generator scope (electrical)
Demand analysis


For the role of part project lead we require a long term commitment of a specialist. The function will evolve during the project according to the following demand analysis.

This is a demand forecast actual requirement may be changed by Ineos based on effective requirements during preparation.

phases scoping tender
preparation RFQ Basic work
preparation Detailed
Work preparation Pre
shutdown shutdown Post
shutdown
period 1-1-2020 1-3-2019 1-6-2020 1-11-2020 1-2-2021 1-4-2021 15-4-2021 / 1-7-2021
1-3-2020 1-6-2020 1-11-2020 1-2-2021 1-4-2021 15-4-2021 1-7-2021 1-10-2021
FTE 0.2 0.2 0.1 0.3 0.4 0.6 1.0 0.2
hrs 60 100 100 200 260 80 600 100

Je profiel

For the role of Part project lead rotating equipment, we are looking for a senior specialist with extensive experience with execution of outages on both steam and gas turbine installations. The person has to be able to present a number of references were he has performed this role within a standing organization. These references should clarify his knowledge on the following topics:

Scope management, based on operating profile and maintenance manual develop an outage scope.
Sourcing and procurement, proven and good network within the turbine vendor organization,
Project management, proven skills in work preparation and coordination both in preparation fase and execution fase.
Coordination and planning, proven capability in coordination and planning of multiple contractors in a limited time and space environment
Quality, Proven knowledge of quality procedures, standards, and norm for turbine installations.
Knowledge to adequately interpret impact of findings and provide advice.
Safety, certified according to safety standards and proven reference to good working practice and safety protocols.
Financial reporting, proven record on transparent financial reporting on all project aspects. Preferably, the Part project lead already has knowledge off:
Ineos oxide working procedures and safety standards,
Site awareness and situational knowledge,
Siemens TLRI Steam turbine,
SGT 800 gas turbine installation and maintenance execution,

Misschien zijn deze vacatures ook interessant voor u

Equipment Reliability Engineer
We are searching for an Equipment Reliability Engineer for our client in the region Terneuzen.
Mechanical
(NL) Zeeland
Master
BEKIJK
Referentie:
1891
Projectfase:
Engineering
Discipline:
Mechanical
Functie:
Engineer
Functie niveau:
Lead
Regio:
(B) Antwerpen
Opleiding:
Master
Ervaring:
8-15 jaar
Contracttype:
Freelance
Geplaatst:
01-01-1970
Job Alert ontvangen?
Schrijf je in
Onze referenties

Wij gebruiken cookies om uw gebruikservaring te optimaliseren en het webverkeer te analyseren. Lees meer over hoe wij cookies gebruiken en hoe u ze kunt beheren door op 'Instellingen' te klikken. Als u akkoord gaat met ons gebruik van cookies, klikt u op 'Alle cookies toestaan'.